 backup job in schedule

Author  Topic 

Hitesh Shah
Yak Posting Veteran

80 Posts

Posted - 2007-05-17 : 07:08:35
Whenever I attempt to edit/run/... a scheduled job, I get the error message:
"Error 14258: Cannot perform this operation while SQL ServerAgent is
starting. Try again later."
I also notice that all scheduled jobs have "Date/time not available" in
"Next Run Date".

SQL server Agent is not starting now, it has already started (Alerts and
Operators can be edited without a problem). The server is SQL2000, SP3a.

rmiao
Master Smack Fu Yak Hacker

7266 Posts

Posted - 2007-05-17 : 09:58:57
Double check status in services applet, maybe it is in starting. Have to fix that if so.