vbugarsk
Starting Member
1 Post |
Posted - 2009-06-22 : 15:07:50
|
| I have table ResourceRequirement, which has three columns (TaskID int, Date datetime, Hours int)I also have Calendar table with (Date datetime, IsWorkDay bit)What I would like to have is sproc/function which will have following parameters:@TaskID int,@EndDate datetime,@Hours intBasically, function should insert hours for each day in ResourceRequirement table, based on 8-hours working time, but taking into account only working days.For example:Function(1000, '20090622', 20)should insert following records into ResourceRequirement table:TaskID Date Hours1000 2009-06-22 81000 2009-06-19 81000 2009-16-18 4since 2009-06-21 and 2009-06-20 are not working days (have IsWorkDay=0 in Calendar table).Any idea, maybe with recursive queries ?? |
|
|
|
|
|