Posted - 2009-01-23 : 16:46:34
|
| Hi, I need to subtract "Start" date from the "End" Date. But I need to exclude weekends. Suppose one job has been started on the Friday and finished on Tuesday, then the difference should return 3 days instead of 5, because I don't need weekends.I have used the following for finding difference: DATEDIFF(DAY, DATEADD(second, tm.T1, '1969-12-31 8:00:00 PM'), DATEADD(second, tm.T10, '1969-12-31 8:00:00 PM'))) Thank you. |
|
|
nathans
Aged Yak Warrior
938 Posts |
|
|
mukhan85
Starting Member
46 Posts |
|
|
nathans
Aged Yak Warrior
938 Posts |
Posted - 2009-01-23 : 18:02:25
|
no problem, thank Jeff! Nathan Skerl |
 |
|
|
|
|
|