hi all,
I got a big problem about log shipping, I don't know how to get exactly next run time of copy and restore job. example: first of all (Copy job): I configure copy job last run: 10:12:00 next run: 10:22:00 (frequency 10 minute)
then, I want to reconfigure with frequency 15 minute. but I got result below: last run: 10:12:00 next run: 10:18:00
(exactly result must is : last run: 10:12:00 next run: 10:27:00)
I don't know why? please help me to clear it. thanks so much! (My English too bad )
 --
Vo Van Hao |
|
biswajitdas
Starting Member
44 Posts |
Posted - 2012-01-11 : 14:00:21
|
did you reconfigure the job at 10:03:00 ?