ravindra.nadavala
Starting Member
4 Posts |
Posted - 2008-07-18 : 00:11:01
|
| hi,I have table called Test(TaskId(identity column),StartDate date,EndDate date)insert into Test values('12/12/2008','12/20/2008')insert into Test values('11/11/2008','12/20/2008')then i have to alter table like alter table Test add (workingdays int)update the table set workingdays = no.of business days(startdate,enddate) for each taskidi tried a lot...but i am not getting, by where condtion i can able to do this ..i don't know how to do this for all the records Thanks in AdvanceRavindra.N |
|
|
dexter.knudson
Constraint Violating Yak Guru
260 Posts |
Posted - 2008-07-18 : 00:28:31
|
| This is complicated because I assumue you will need to cater for public holidays as well as weekends. Are the public holidays the same for all users doing tasks? |
 |
|
|
dexter.knudson
Constraint Violating Yak Guru
260 Posts |
Posted - 2008-07-18 : 00:30:19
|
| In Australia, for example, there are some public holidays at the state level. And also, for example, I understnad in New Zealand, a regional area or city has a holiday different to otehr areas. |
 |
|
|
ravindra.nadavala
Starting Member
4 Posts |
Posted - 2008-07-18 : 01:19:39
|
hi,please conider Sat and sunday are holidays...ThanksRavindra.Nquote: Originally posted by dexter.knudson In Australia, for example, there are some public holidays at the state level. And also, for example, I understnad in New Zealand, a regional area or city has a holiday different to otehr areas.
|
 |
|
|
sunil
Constraint Violating Yak Guru
282 Posts |
Posted - 2008-07-18 : 02:36:59
|
| http://www.sqlteam.com/forums/topic.asp?TOPIC_ID=105208 |
 |
|
|
ayamas
Aged Yak Warrior
552 Posts |
Posted - 2008-07-18 : 02:38:49
|
| Try thisdeclare @Test as table(TaskId int identity(1,1),StartDate datetime,EndDate datetime)insert into @Test values('12/12/2008','12/20/2008')insert into @Test values('11/11/2008','12/20/2008')select dates as BusinessDays from (select dateadd(dd,number,StartDate)as dates,TaskId from @test inner join master.dbo.spt_values on master.dbo.spt_values.type='p'where master.dbo.spt_values.number<=datediff(dd,startdate,enddate))t where datename(dw,dates)<> ('Saturday') and datename(dw,dates)<> ('sunday') |
 |
|
|
ayamas
Aged Yak Warrior
552 Posts |
Posted - 2008-07-18 : 02:40:03
|
quote: Originally posted by sunil http://www.sqlteam.com/forums/topic.asp?TOPIC_ID=105208
Missed by minute and a half. |
 |
|
|
SwePeso
Patron Saint of Lost Yaks
30421 Posts |
Posted - 2008-07-18 : 03:28:08
|
It's better if you can calculate the days instead of counting themcreate function workdays_jeff(@StartDate datetime, @EndDate datetime) returns float asbeginreturn CAST( ( (DATEDIFF(dd,@StartDate,@EndDate)+1) -(DATEDIFF(wk,@StartDate,@EndDate)*2) -(CASE WHEN DATENAME(dw,@StartDate) = 'Sunday' THEN 1 ELSE 0 END) -(CASE WHEN DATENAME(dw,@EndDate) = 'Saturday' THEN 1 ELSE 0 END) ) -(CASE WHEN DATENAME(dw,@StartDate) = 'Sunday' or DATENAME(dw,@StartDate) = 'Saturday' THEN 0 ELSE CAST(CONVERT(CHAR(12),@StartDate,114) AS DATETIME) END) -(CASE WHEN DATENAME(dw,@EndDate) = 'Sunday' or DATENAME(dw,@EndDate) = 'Saturday' THEN 0 ELSE (1.0-CAST(CONVERT(CHAR(12),@EndDate,114) AS DATETIME)) END) AS FLOAT)end E 12°55'05.25"N 56°04'39.16" |
 |
|
|
ravindra.nadavala
Starting Member
4 Posts |
Posted - 2008-07-18 : 04:51:56
|
its working great,but i need to count the working days and update the workingdays column in the table, for each TaskId..thanks in advance.quote: Originally posted by ayamas
quote: Originally posted by sunil http://www.sqlteam.com/forums/topic.asp?TOPIC_ID=105208
Missed by minute and a half.
|
 |
|
|
ravindra.nadavala
Starting Member
4 Posts |
Posted - 2008-07-18 : 04:58:54
|
hi,thanks for reply.. i need to dothis for each record in the table and update the same table column working days with this count ..is this possible through function or procedurequote: Originally posted by ravindra.nadavala its working great,but i need to count the working days and update the workingdays column in the table, for each TaskId..thanks in advance.quote: Originally posted by ayamas
quote: Originally posted by sunil http://www.sqlteam.com/forums/topic.asp?TOPIC_ID=105208
Missed by minute and a half.
|
 |
|
|
visakh16
Very Important crosS Applying yaK Herder
52326 Posts |
Posted - 2008-07-18 : 05:13:05
|
quote: Originally posted by ravindra.nadavala its working great,but i need to count the working days and update the workingdays column in the table, for each TaskId..thanks in advance.quote: Originally posted by ayamas
quote: Originally posted by sunil http://www.sqlteam.com/forums/topic.asp?TOPIC_ID=105208
Missed by minute and a half.
you can convert the code into a UDF with two parameters and call it for each taskid by passing the dates |
 |
|
|
|