| Here's what I need to do. I want to be able to calculate 5 business days based on a given date. So for example if the date is 4/4/2010 then 5 business days from there should be 4/11/2010 (not counting 4/4) |
|
|
pk_bohra
Master Smack Fu Yak Hacker
1182 Posts |
Posted - 2010-03-05 : 00:46:18
|
| By business days you mean Monday to Friday or all days ?Secondly, the data you gave in example (4/4/2010) is sunday and the output you want is also sunday (4/11/2010).Can you please post more sample data..Regards,Bohra |
 |
|
|
Sachin.Nand
2937 Posts |
Posted - 2010-03-05 : 01:16:19
|
quote: Originally posted by steppinthrax Here's what I need to do. I want to be able to calculate 5 business days based on a given date. So for example if the date is 4/4/2010 then 5 business days from there should be 4/11/2010 (not counting 4/4)
Do you have a calendar table where u define your business days?If not then please refer here.http://visakhm.blogspot.com/2010/02/generating-calendar-table.htmlPBUH |
 |
|
|
|
|
|