Hi,

I have this SQL to display the assignment name and due date:
* Select AssignmentName, DueDate from AssignmentTable

Results:
Assignment1, 1/2/2004
Assignment2, 1/2/2004
Assignment3, 1/3/2004
Assignment4, 1/4/2004
Assignment5, 1/4/2004

Is it possible to include a column to flag 4 weeks before the Due Date ?

Eg,
Assignment1, 1/2/2004,
Assignment2, 1/2/2004,
Assignment3, 1/3/2004,
Assignment4, 1/4/2004, Need Attention
Assignment5, 1/4/2004, Need Attention

Matthew

timmy
Master Smack Fu Yak Hacker

1242 Posts

Posted - 2004-05-31 : 19:29:39
It is possible.

Use the DateAdd function to calculate the +- 4 weeks e.g. DateAdd(d, 28, AssignmentDate)
And use the IIF function to determine if the calculated date is before or after the current date.

Check out the Access/JET help files for more info.

Tim